40T Hydraulic Gantry Case Study: Low-Headroom Machine Installation

♠     Customer: Large industrial printer & packaging plant

♠     Application: Low-headroom installation of a long, heavy machine module on a concrete plinth

♠     Load type: Rigid machine section with sensitive components (requires fine alignment)

♠     Equipment supplied: 40-ton hydraulic gantry (two-post), header beam, powered pump unit, steel track, rigging set, remote control

♠     Outcome: Safe, synchronized lift-and-set with millimeter-level alignment and minimal line downtime

Description

40T Hydraulic Gantry Case Study: Low-Headroom Machine Installation

 

40T Hydraulic Gantry Case Study: Low-Headroom Machine Installation

Customer Challenge

 

Installing a bulky machine inside an existing hall meant:

♣  Low roof height / limited headroom—mobile crane access was impossible.

♣  Tight aisles & finished floors—no heavy crane outriggers allowed; point loads had to be controlled.

♣  Precision alignment—the machine needed to land on anchor bolts along a concrete plinth and match line height.

 

 

 

Why a 40-Ton Hydraulic Gantry

 

Compared with an overhead crane or mobile crane, a hydraulic gantry:

♣  Works comfortably under low ceilings; telescopic cylinders create lift without boom clearance issues.

♣  Rolls on track to traverse the load in small increments—ideal for “lift, move a little, set” workflows.

♣  Offers synchronized control (±1–3 mm typical) for accurate positioning on foundations.

♣  Brings lower site disruption—compact footprint, no exterior crane logistics.

 

 

MOT Crane Solution & Method

 

♣  Track layout & load study

Temporary steel rails fixed along the plinth; floor bearing checks done to keep concrete within allowable pressure.

 

♣  Header beam & rigging

Spreaders and soft slings protected machine skins; lift points balanced for center-of-gravity control.

 

♣  Synchronized lift

Gantry raised the load just above final height; remote pendant maintained cylinder synchronization.

 

♣  Slow traverse & set

Inch-by-inch travel along rails; final set on grout pads with dial indicator checks.

 

♣  Commissioning

Oil-free wipe-down, torque checks, documentation and operator briefing.

 

♣  Result

Installation finished within a planned shift, alignment achieved to tolerance, and the production line could proceed with wiring and commissioning the same day.

 

 

What This Means for Plant Owners

 

♣  No roof modifications or temporary beam installs

♣  Short shutdowns and predictable schedules

♣  High positioning accuracy for anchor-bolt or plinth sets

♣  Lower total project cost versus bringing in big mobile cranes indoors

 

 

Frequently Asked Questions (FAQ)

 

♣  Can a 40-ton hydraulic gantry crane work if my ceiling is only 4–5 meters?

Yes. With a collapsed height around 2.5–3.2 m and a modular header beam, a 30-ton gantry is designed for low-headroom lifts inside factories.

 

♣  What floor information do you need?

Concrete thickness, grade, and reinforcement. We calculate line loads of the gantry bases/rails and recommend pad size or shoring if needed.

 

♣  How is synchronization achieved?

The power pack and valve manifold balance cylinder flow; operators use a remote pendant to keep posts level during lift, traverse, and set.

 

♣  What documents will I receive?

Load study summary, rigging plan, track layout, method statement, inspection checklist and commissioning records (on request).

 

♣  Can you supply rental + operators?

Depending on region, we can supply equipment, supervision, or turnkey service via our partner network. Ask our team for availability.

Parameter

40T Hydraulic Gantry Crane Exported to Spain

 

Specifification HYDRAULIC GANTRY CRANE 40T
Load capacity of each main beam 40T
Maximum lifting force per column 40T
Weight of each main beam 5T
Weight of each lifting unit 3.5T
Weight of trolley 0.5T
Span 12m
Lifting stroke 2m-3.5m
Number of jacking units 2pcs
Lifting/falling speed 0-1 m/min
Trolley (lifting point) moving speed 0-5 m/min
Gantry moving speed 0-10 m/min
Crane power system Electric power, hydraulic system
Control mode Remote control operation
Working pressure 20-25Mpa
Working environment -10℃~+40℃
Power supply 380v 50hz 3P
Download Specifications
GET QUOTES

    ©Copyright 2025 By Jiangsu Morton Marine Technology CO.,LTD All Rights Reserved
    en_USEnglish